# Delivery Planning — Risk & Sequencing Rationale > The why behind the Bolt order. **Bolt** is one build pass over a piece of the > work, ending in something that runs. The economic order chosen here is: value > core first, then the higher-unknown parallel pair, then integration. ## Sequencing argument The chosen order balances **early working software** (Q1=A) with **de-risking the uncertain parts early** (Q6=B,C,D — the user's worries: funnies unpredictability, AI drafting quality, review-handoff reliability). - **Bolt 1 — `generator` core first (value/skeleton case).** Builds the central, highest-confidence capability: CLI → content → layout → emit → A4 print. The paper works end-to-end with hand-written content early, so the highest-value surface (the printable broadsheet) is proven before the exotic parts land. This also naturally satisfies the affirmed "no separate walking skeleton": the first Bolt IS a thin end-to-end slice (markdown in → A4 page out) without calling it one. - **Bolts 2a/2b — `ai-draft` and `funnies` in parallel (risk-reduction).** The two most unpredictable units — AI copy quality and content-derived puzzle/ cartoon generation — are independent, so they build concurrently (Q4=B). Both de-risk the user's stated worries (Q6=B,C) before integration. Each is also independently testable (DraftBundle contract; puzzle+cartoon output). - **Bolt 3 — integration last.** Wires the two new units into the core and completes the full-chain fidelity (multi-page print, photo embed, per-article review handoff). The review-handoff reliability worry (Q6=D) is addressed here against the file:// no-server constraint. ## Reference heuristic No formal WSJF score (Q2=A). The order follows a pragmatic mix: **value-first + risk-reduction + dependency-aware**. It is coherent with Reinertsen's CD3-style reasoning (deliver value early while sequencing the high uncertainty soon enough to learn from it), but we did not compute a numeric score. ## Deviation-from-topology note The Bolt order **does not strictly follow 2.7's topological order**. Topology says `generator` depends on `ai-draft` and `funnies`; a strict topological walk would build ai-draft + funnies first. We deviate deliberately: **Bolt 1 builds `generator` with simple/sample content first** (no ai-draft/funnies needed for the core hand-written path), then the independent pair in parallel (Bolt 2a/2b), then integration (Bolt 3). This is justified by Q1=A (value core early) and the parallelism in Q4=B. The deviation is captured here as the stage requires. ## Rationale | Bolt | Rationale | |---|---| | Bolt 1 | Value core, highest confidence, end-to-end early | | Bolt 2a | Independent + user worry (AI quality/drafting) — de-risk | | Bolt 2b | Independent + user worry (funnies) — de-risk | | Bolt 3 | Integration + full fidelity (incl. print-fidelity worry Q6=A) |